Construction Update on the twin towers east of Skyline

Construction Bulletins:

November 9, 2018 UPDATE

  • Earthwork activities will continue during select Saturdays in an effort to expedite the mass excavation scope and to minimize overall night hauling durations.
  • Excavation and Shoring is approximately 90% with completion of mass excavation projected to be the middle of November.
  • Demobilization of equipment will occur on November 17th – There will be a mobile crane brought in to pull equipment out of the hole as well as place three trailers on the scaffolding.  This will require road closures on Columbia and Terry for that day.
  • Night hauling is ongoing and is projected to carry on until the end of excavation – scheduled to complete in November.
  • December 7-9 the conveyor will be demobilized and the tower crane will be erected. These activities will require road closures on Columbia and Terry.
  • Detail excavations and structural cast in place concrete elements will begin in November. This will require deliveries of reinforcing, formwork and concrete redi-mix. Concrete pumps will be staged on Terry Avenue for various concrete pours.
  • The site will be shut down for Thanksgiving from Thursday November 22, 2018 through Sunday November 25, 2018.
This entry was posted in Community Engagement Group, environment, In the Neighborhood, Skyline Info. Bookmark the permalink.