June 3, note that view. Note original crane is attached to elevator core.
December 3, new crane (leftmost) finished, bolted to the roof of the 43-story 5th & Columbia building.
December 10. Within a week, the original crane has been disassembled using the new crane. The replacement is a lighter-limit crane lacking superstructure and with a smaller counterweight, now that all structural steel is in place. An additional floor has gained windows.